2017 – Haldon Dam Remediation: A Case Study of Earthquake Damage and Restoration
John Harris, James Robinson, Ron Fleming
Haldon Dam Remediation: A Case Study of Earthquake Damage and RestorationJohn Harris, James Robinson, Ron FlemingAECOM New Zealand LimitedAECOM New Zealand Limited, Fleming Project Services Limited Haldon Dam is a 15m high zoned earth-fill embankment irrigation dam, located approximately 10 km south-west of Seddon, in the Awatere Valley, New Zealand. The crest and upstream shoulder of the embankment suffered serious damage during the 2013 Cook Strait earthquakes, and the Regulator enforced emergency lowering of the reservoir by 5.5m to reduce the risk of flooding to Seddon Township from a potential dam failure. AECOM was engaged by the owner to carry out a forensic analysis of the damaged dam and subsequently the design of the 2-Stage remedial works. The remedial works addressed the existing dam deficiencies and earthquake damage in order to restore the dam to full operational capacity and gain code compliance certification. Key features oft he approach included holding a design workshop with the owner prior to undertaking detailed design, careful rationalisation of the upstream shoulder to optimise the competing interests of strength and permeability, contractor and regulator involvement in the design and construction process, and balancing risk and constructability with the chimney filter retrofit. This paper presents a description of, and approach to, remedial works solution undertaken to remediate a substandard and earthquake-damaged dam to fully operational status in an area of high seismicity. Applying this approach, the objective of achieving a robust, safe, economical design that was acceptable to the regulators and the owner was achieved.
$15.00
Now showing 1-12 of 47 2981:
Related products
-
$15.00
2017 Papers
2017 – Construction Flood Risk Strategies for Dam Upgrades
Learn moreColleen Baker, Sean Ladiges, Peter Buchanan, James Willey, Malcolm Barker
Dam Owners and Designers are often posed with the question “what is an acceptable flood risk to adopt during the construction of dam upgrade works?” Both the current ANCOLD Guidelines on Acceptable Flood Capacity (2000) and the draft Guidelines on Acceptable Flood Capacity (2016) provide guidance on the acceptability of flood risk during the construction phase. The overarching principle in both the current and draft documents is that the dam safety risk should be no greater than prior to the works, unless it can be shown that this cannot reasonably be achieved.Typically with dam upgrade projects it is not feasible to take reservoirs off-line during upgrade works, with commercial and societal considerations taking precedent. It is therefore often necessary to operate the reservoir at normal levels or with only limited drawdown. The implementation of measures to maintain the risk at or below that of the pre-upgraded dam can have significant financial and program impacts on projects, such as through the construction of elaborate cofferdam arrangements and/or staging of works. This is particularly the case where upgrade works involve modifications to the dam’s spillway.The use of risk assessment has provided a reasonable basis for evaluating the existing and incremental risks associated with the works, such as the requirement for implementation of critical construction works during periods where floods are less likely, in order to justify the As Low As Reasonably Practicable (ALARP) position. This paper explores the ANCOLD guidelines addressing flood risk, and compares against international practice. The paper also presents a number of case studies of construction flood risk mitigation adopted for dam upgrades on some of Australia’s High and Extreme consequence dams, as well as international examples. The case studies demonstrate a range of construction approaches which enable compliance with the ANCOLD Acceptable Flood Capacity guidelines
Learn more -
$15.00
2017 Papers
2017 – Variability between Rainfall Runoff Methods and Observed Floods: Implications for Risk, Design, Dam Operation and Communities in Australia
Learn moreJames Stuart, Michael Hughes
Several recent rain events in Australia have resulted in impoundment flood levels where there was a surprising variability between the Annual Exceedance Probability (AEP) of the flood level and that of the rainfall. The issue was highlighted during the Queensland Flood Commission of Inquiry (QFCI, 2011) by the Queensland Dam Safety Regulator who suggested there may be a problem with design hydrology after a dam safety event that saw impoundment levels of around 1:9000 AEP with a 1:200 AEP catchment rainfall at North Pine Dam, north of Brisbane in 2011. Wide disparities have occurred at Wivenhoe Dam west of Brisbane, at Callide Dam, west of Gladstone and at other locations.
This paper examines the Generalised Short Duration Method (GSDM) (BoM, 2003) and the Revised Generalised Tropical Storm Method (GTSMR) (BoM, 2003) typically used for dam flood capacity assessments in an attempt to explain the variability outlined above and whether it is, in part, exacerbated by the methods themselves.
It finds that processes of generalising rainfall depth, intensity, temporal and spatial characteristics are working together with adopted hydrological methods to contribute to such variability, that in the worst case could lead to PMF levels in dams with much less rainfall than the associated PMP would infer.
Moreover, two key assumptions; that of AEP neutrality (AEP of rainfall is equal to that of the flood) and frequency of PMP based on catchment area, which are the foundations stones of our understanding of flood frequency for large structures, are found to be untested or simply interim advice. This leads to the conclusion that the likelihood of floods in the range 2000 year AEP to PMF may continue to show surprising variability, potentially of an order of magnitude or more, compared to the rainfall AEP.
There is a need for a review of these methods and potentially provision of interim guidance as these methods are currently being used in dam upgrade programs throughout Australia and are also the basis for emergency planning. The identification of these issues concerns current methods and are independent to any discussion on climate change.Prior to commencing, it is worth defining two terms that re-occur throughout the document:
Annual Exceedance Probability (AEP): The probability that a given rainfall total accumulated over a given duration will be exceeded in any one year. AEP Neutrality is the theory that assumes the probability of the rainfall can be transferred to the resulting flood.Average Variability Method (AVM): Technique for estimating design temporal pattern of average variability to ensure AEP Neutrality in transition from PMP to PMP design flood
Learn more -
$15.00
2017 Papers
2017 – Lessons Learned and the impacts of Cyclones Debbie and Marcia on Queensland’s Emergency Planning and Guidelines
Learn morePeter Allen and Mark Rhimes
Recent tropical cyclones have had significant impacts on coastal Queensland and produced significant inflows into a large number of major dams with the triggering of a number of Emergency Action Plans for downstream release hazards. While there were several floods of record, there were no significant dam safety incidents. The dams seemed to have been blamed for a lot of this flooding even though they provided significant flood mitigation. This paper will cover the emergency responses to these events, the public perceptions and the associated third party reviews of these events. Community expectations and the ability to undertake post flood event assessments of dam operations is also driving such investigations.This paper will also discuss the consequential updates being made to Queensland Emergency Action Planning Guidelines to encourage effective engagement with local emergency planners and other stakeholders in the development of these guidelines.
Learn more -
2017 Papers
2017 – Certainty in Uncertainty: Navigating Environmental Impact Assessment Regulatory Processes
Learn moreGeraldine Squires
There is increased pressure from stakeholders for projects to include evaluation of emerging broader development issues within the environmental assessment process. These emerging issues are not well documented or understood and at the forefront of untested preliminary government policy positions.
Agencies expect proponents to invest in evaluating these matters outside of typical assessment practices. Requests are made late in the evaluation and approval process.Assessmen involves matters not directly related to the project or within the proponent’s control and occurs late in the project development cycle.
The Lower Fitzroy River Infrastructure Project (LFRIP) was identified through the Central Queensland Regional Water Supply Study in 2006, as a solution to secure future water supplies for the Rockhampton, Capricorn Coast and Gladstone regions. The Gladstone Area Water Board and SunWater Limited, as proponents, propose to raise the existing Eden Bann Weir and construct a new weir at Rookwood on the Fitzroy River in Central Queensland.
The LFRIP environmental impact statement (EIS) was approved, subject to conditions, by the Queensland Coordinator-General in December 2016 and the Commonwealth Minister for the Environment and Energy in February 2017. Achieving conditions that will realise positive environmental outcomes while simultaneously achieving project objectives, particularly with regard to timeframes and costs, was not without its challenges.
The EIS was developed in accordance with the requirements of the State Development Public Works Organisation Act 1971 (Qld) and the Commonwealth’s Environment Protection and Biodiversity Conservation Act 1999, including an extensive stakeholder consultation programme. These regulatory requirements are well understood and applied to projects as normal accepted practice. They ensured that potential project impacts and benefits were identified, that appropriate levels of effort were applied to investigations to establish baseline conditions and that risks to and impacts on environmental (including social and cultural) matters were adequately mitigated and managed.
The environment is not static. Emerging issues and perceptions results in regulation and policy changes in response to political and social drivers. During the development of the EIS both new legislation and new policies were imposed on the project.New legislation resulted in additional assessment around matters previously considered mitigated and managed (fish passage). New legislation introduced new matters for assessment (connectivity). Collaboration and engagement with stakeholders were key to understanding the applicability of these elements to the project and for developing an approach to address the legislative requirements late in the project’s development and assessment process.
In Queensland,policy is emerging to mitigate and manage impacts of development on the Great Barrier Reef World Heritage Area’s universal values. The EIS was required to address the direct project impacts on water quality and the impacts arising because of the LFRIP (facilitated development). Water secured by the LFRIP is for urban, industrial and agricultural purposes. Urban and industrial developments are well regulated and subject to specific environmental approvals processes. Use of water for agricultural purposes, intensive irrigated agriculture in particular,is less regulated. Policies developed are reactive and require individual projects to address these impacts.In the absence of regulatory guidelines for assessment of consequential impacts, the project adopted a collaborative approach. The proponents established a working group, including State and Commonwealth technical agencies. This allowed for robust and scientifically defendable methodologies to be developed and agreed upfront. Streamlining the approach by including key decision makers assisted in managing expectations and focused the assessment on realistic and achievable outcomes relative to the project. The result was defendable outcomes allowing timely decision making and avoided rework as much as possible.
This paper describes developments in environmental assessment relating to new and augmented weirs.
Learn more -
$15.00
2017 Papers
2017 – Detailed Seismic Hazard Assessment of Mt Bold Area: Comprehensive Site-Specific Investigations on Willunga Fault
Learn moreZivko R. Terzic, Mark C. Quigley, Francisco Lopez
The Mt Bold Dam, located in the Mt Lofty Ranges in South Australia, is a 54m high concrete arch-gravity dam that impounds Adelaide’s largest reservoir. The dam site is located less than 500m from a suspected surface rupture trace of the Willunga fault.Preliminary assessments indicate that Mt Bold Dam is likely to be the dam with the highest seismic hazard in Australia, with the Flinders Ranges-Mt Lofty region experiencing earthquakes of sufficient magnitude to generate shaking damage every 8-10 years on average. Prior evidence suggests that the Willunga Fault is likely capable of generating M 7-7.2 earthquakes.As part of the South Australia Water Corporation (SA Water) portfolio of dams, Mt Bold Dam is regularly reviewed against the up-to-date dam safety guidelines and standards. SA Water commissioned GHD to undertake detailed site-specific geophysics, geotechnical and geomorphological investigations, and a detailed site-specific Seismic Hazard Assessment (SHA) of the Mt Bold Dam area. The results of this investigation will be used to inform decisions related to planned upgrade works of the dam.Geomorphological mapping of Willunga Fault, detailed geological mapping, analysis of airborne lidar data, geophysical seismic refraction tomography and seismic reflection surveys,and paleoseismic trenching and luminescence dating of faulted sediments was conducted to obtain input parameters for the site-specific SHA.Discrete single-event surface rupture displacements were estimated at ~60 cm at dam-proximal sites. The mean long-term recurrence interval (~37,000 yrs) is exceeded by the quiescent period since the most recent earthquake (~71,000 yrs ago) suggesting long-term variations in rupture frequency and slip rates and/or that the fault is in the late stage of a seismic cycle. The length-averaged slip rate for the entire Willunga Fault is estimated at 38 ± 13 m / Myr. Shear wave velocity (Vs30) of the dam foundations was estimated based on geotechnical data and geological models developed from geophysical surveys and boreholes drilled through the dam and into the foundation rock. The nearest seismic refraction tomography (SRT) lines were correlated with the boreholes and those velocity values used in the Vs30 parameter determination. All relevant input parameters were included into seismic hazard analysis with comprehensive treatment of epistemic uncertainties using logic trees for all inputs.Deterministic Seismic Hazard Analysis (DSHA) confirmed that the controlling fault source for the Mt Bold Dam site is Willunga Fault, which is located very close to main dam site (420m to the West).For more frequent seismic events (1 in 150, 1 in 500 and 1 in 1,000 AEP), the probabilistic analysis indicates that the main seismic hazard on the dam originates from the area seismic sources (background seismicity).Based on deaggregation analysis from the site specific Probabilistic Seismic Hazard (PSHA), the earthquakes capable of generating level of ground motion for the 1 in 10,000 AEP event can be expected to occur at mean distances of approximately 22km from the dam site(with the mean expected magnitude atMt Bold Damsite estimated at Mw >6).For less frequent (larger) seismic events, the contribution of the Willunga Fault to the seismic hazard of Mt Bold Dam can be clearly noted with Mode distance in the 0-5 km range, which indicates that most of the seismic hazard events larger than the 1 in 10,000 AEP comes from the Willunga Fault. The Mode magnitudes of the events are expected to be Mode Magnitude at Mw= 6.6 for a segmented Willunga Fault scenario, and Mw= 7.2 for a non-segmented fault scenario.Consideration was also given to the upcoming update of the ANCOLD Guidelines for Earthquake, which calls for the determination of the Maximum Credible Earthquake (MCE) on known faults for the Safety Evaluation Earthquake (SEE) of “Extreme” consequence category dams. The MCE for Mt Bold Dam was estimated from the DSHA; in terms of acceleration amplitude, the MCE event approximately equals the 1 in 50,000AEP seismic events.
Learn more