2017 – Dam and Foundation Repsonses to the 2016 MW7.8 Kaikōura Earthquake in New Zealand
Andrew Balme, Dan Forster, Tim Logan
The MW7.8 Kaikōura earthquake on 14 November 2016, ruptured over 20 faults during the initial shaking,which lasted nearly two minutes. A complex series of fault ruptures propagated northeast for nearly 180 km from the initial rupture location. Instrumentation from dams across New Zealand shows that whilst most dams did not suffer physical damage, piezometric responses were measured in dams and their foundations. Earthquake related changes in seepage regimes are not unusual and depend on the characteristics of the ground motions,and site specific characteristics that influence how a dam and its foundation respond to ground motions. The ability to measure a piezometric response in a dam or foundation is heavily influenced by the instrumentation network and method of monitoring. Data collected during events such as the Kaikōura earthquake provides valuable information for both characterising performance of a dam during the event, and assisting future analysis such as failure mode assessments. Careful consideration must be given to the scope of installed instrumentation and the frequency of monitoring in order to provide these benefits,and the robustness of the system to ensure it adequately survives the event.
$15.00
Now showing 1-12 of 47 2981:
Related products
-
$15.00
2017 Papers
2017 – Construction of Borinquen Dam 1E for the Panama Canal Expansion
Learn moreJames Toose, Lelio Mejia, Jorge Fernandez
The recently completed Panama Canal Expansion project required construction of a new, 6.7-km-long channel at the Pacific entrance to the Panama Canal, to provide navigation access from the new Post-Panamax locks to the existing Gaillard Cut section of the Canal. The new channel required construction of four new dams adjacent to the existing canal, referred to as Borinquen Dams 1E, 2E, 1W, and 2W. The dams retain Gatun Lake and the Canal waterway approximately 11 m above the level of Miraflores Lake and 27m above the Pacific Ocean.The largest of the dams, Dam 1E, is 2.4km long and up to 30 m high. The dam abuts against Fabiana Hill at the southern end, and against the original Pedro Miguel Locks at the northern end. This paper provides an overview of the key challenges in construction of Dam 1E including the foundation, seepage cut-offs and embankment.
Learn more -
$15.00
2017 Papers
2017 – An Updated National Seismic Hazard Assessment for Australia: Are We Designing for the Right Earthquakes?
Learn moreT. Allen, J. Griffin, M. Leonard, D. Clark and H. Ghasemi
Geoscience Australia (GA) has embarked on a project to update the seismic hazard model for Australia through the National Seismic Hazard Assessment (NSHA18) project.The draft NSHA18 update yields many important advances on its predecessors, including: 1) calculation in a full probabilistic framework using the Global Earthquake Model’s OpenQuake-engine; 2) consistent expression of earthquake magnitudes in terms of moment magnitude, MW; 3) inclusion of epistemic uncertainty through the use of alternative source models; 4) inclusion of a national fault-source model based on the Australian Neotectonic Features database; 5)the use of modern ground-motion models; and 6)inclusion of epistemic uncertainty on seismic source models, ground-motion models and fault occurrence and earthquake clusteringmodels.The draft NSHA18 seismic design ground motions are significantly lower than those in the current (1991-era) AS1170.4–2007 hazard map at the 1/500-year annual ground-motion exceedance probability (AEP) level. However, draft values at lower probabilities (i.e., 1/2475-year AEP) are entirely consistent,in terms of the percentage area of land mass exceeding different ground-motion thresholds,with other Stable Continental Regions(e.g.,central & eastern United States). The large reduction in seismic hazard at the 1/500-year AEP level has led to engineering design professionals questioning whether the new draft design values will provide enough structural resilience to potential seismic loads from rare large earthquakes. This process underscores the challenges in developing national-scale probabilistic seismic hazard analyses (PSHAs)in slowly-deforming regions, where a 1/500-year AEP design level is likely to be much lower than theANCOLD Maximum Credible Earthquake (MCE) ground motions. Consequently, a robust discussion among the Standards Australia code committee, hazard practitioners and end users is required to consider alternative hazard and/or risk objectives for future standards.Site-specific PSHAs undertaken for owners and operators of extreme and high consequence dams general-ly require hazard evaluations at lower probabilities than for typical structural designas recommended in AS1170.4.However, modern national assessments, such as the NSHA18, can provide a benchmark in terms of recommended seismicity models, fault-source models, ground-motion models, as well as hazard values, for low-probability site-specific analyses.With a new understanding of earthquake processes in Australia leading to lower ground-motion hazard values for higher probability events (e.g.,1/500-year AEP), we should also ask whether the currently recommended design probabilities provide an acceptable level of seismic resilience to critical facilities (such as dams)and regular structures.
Learn more -
$15.00
2017 Papers
2017 – Tullaroop Dam: Ongoing Cracking and Unusual Pore Water Pressure Response in a 60 Year Old Earth Embankment
Learn moreGavan Hunter, David Jeffery and Stephen Chia
The Main Embankment at Tullaroop Dam in central Victoria is a 43 m high earthfill embankment with a very broad earthfill zone and rockfill zones at the outer toe regions. There has been an extensive history of cracking within the Main Embankment since formalisation of visual inspections in 1987.Widespread cracking has been observed on the crest and downstream shoulder. Cracking on the crest has mainly been longitudinal, but transverse cracks have also been observed. Cracking on the downstream shoulder has comprised longitudinal, diagonal and transverse cracking. In April 2004, a 60 mm wide diagonal crack opened on the downstream shoulder of the left abutment (from crest to toe) and Goulburn-Murray Water constructed a local filter buttress in 2005/06 on the left abutment. In 2011/12 a longitudinal crack opened up on the upper downstream berm toward the right abutment. The crack was initially 15m long and 10 to 215 mm wide, then propagated several months later to 70 m in length, 40 to 50 mm width and greater than 3 m in depth.In May 2011 three piezometers within the earth fill core recorded a very rapid rise in pore water pressure equivalent to 12 to 13 m pressure head above their previous readings. The piezometers were located on the same alignment (upstream to downstream) and were located below the crest and downstream shoulder, and the rise was to levels close to and above the embankment surface. The piezometers then showed a steady fall with time returning to the pre rise levels after 4 to 6 weeks.In 2015/16 Goulburn-Murray Water undertook dam safety upgrade works to reduce the risk of piping through the Main Embankment by extension of the filter buttress across the full width of the embankment. During these upgrade works, very deep (greater than 5 m) and extensive transverse cracks were observed in the embankment over relatively subtle slope changes on the right abutment.Thecracking and pore water pressure behaviour in the Main Embankment at Tullaroop Reservoir present an important case study. The paper provides details on the cracking and postulated crack mechanisms, and the rapid pore water pressure rise and postulated mechanisms. A summary of the upgrade works is also provided.
Learn more -
$15.00
2017 Papers
2017 – Tropical Cyclone Debbie – A SunWater Experience
Learn moreMichael Hughes, James Stuart
Tropical Cyclone Debbie (TC Debbie) formed in the Coral Sea on Saturday 25th March, 2017 and developed into a category 4 system that crossed the coast near Proserpine, Queensland with the eye passing very close to Peter Faust Dam. TC Debbie, later becoming Ex-TC Debbie embarked on a tour of SunWater infrastructure (See Figure 1). Of 23 referable dams managed or owned by SunWater in Queensland, only 3 had no inflows with spills resulting at twelve locations. The paper describes the varied experiences of SunWater with relation to preparation for, and operations during TC Debbie. Some key areas of interest to other dam owners include;
- Uncertainty around forecasts;
- Flash flood destruction of key hydrographic equipment;
- A review into dam operation;
- Returning a spillway construction site touse;
- A ‘direct hit’ by the eye of TC Debbie over Peter Faust Dam catchment;
- Successful prediction of Cyclone rainfall temporal patterns; and
- A record flood influenced by land use with learnings for flood risk assessments.
-
$15.00
2017 Papers
2017 – An Innovative Approach to Determine Particle Size Distribution for Rockfill Material
Learn moreZerui Lu, Behrooz Ghahreman-Nejad, Mahdi M. Disfani
Particle characterisation like size distribution and shape can greatly affect the mechanical behaviour of granular materials, and is closely related to the economics for engineering projects. For rockfill material in embankment dam construction, the particle size distribution (PSD) is fundamental to the design, quality control and numerical modelling. Traditionally, particle size distribution for engineering materials is obtained through physical sieving. However, with rockfill material, the size varies significantly and can range from gravels (+2mm) to cobbles (+60mm) and boulders (+200mm) with the maximum size usually limited to 1m, which makes the conventional sieving process considerably difficult to conduct as well as being time-consuming. Meanwhile, the advanced technology in computer image processing has created many possibilities in characterising particles within digital photographs, and therefore can be utilised as an effective alternative to the conventional sieve analysis. This method has been in use mainly in the mining industry over the past two decades to assist with rock fragmentation and process monitoring and control. Notwithstanding, the use of this technique in the dam industry for quality control of rockfill material has been rare. Thus, an innovative approach is proposed in this paper to estimate the PSD curves for rockfill material using image analysis along with the latest developments in aerial photography. The results of PSD analysis using the image processing software Split Desktop are presented and compared with the results from sieve analyses for verification. Recommendations are made to improve the process and increase the accuracy of the outcome. It is demonstrated that the proposed method has a reasonable accuracy and is a viable option for quality control in construction of rockfill structures such as rockfill embankment dams.
Learn more