2010 – How to build a dam – just ask the community?
Cat McConkey, Zarmina Nasir, Rachel Caoil
The Enlarged Cotter Dam (ECD) is the first major project to be assessed and approved under the new planning regime in the Australian Capital Territory (ACT). ACTEW chose the ECD as its highest priority option in securing Canberra’s water supply for the future because of its relative economic benefit to the community, reliability of water supply, technical feasibility and comparatively low environmental impact.
The planning and construction of large dams has been reduced from a typical 10 plus years to four years in the ACT and surrounds for the ECD. Australian and International Dam design and construction has significantly developed from a time when dam approvals focused on engineering, economics and constructability to now include regulatory planning processes that seek to reconcile environmental, social and economic impacts.
This paper explores and contrasts the experience of securing approvals for the ECD in 2009 to past experiences of dam planning approvals and consultation processes.
$15.00
Now showing 1-12 of 41 2974:
Related products
-
$15.00
2010 Papers
2010 – Assessment of flow-induced vibration in radial gates during extreme flood
Learn moreKaren Riddette, David Ho
Recent dam safety reviews of a number of Australian dams have identified that the arms of raised radial gates may be partially submerged by extreme flows which exceed the original design flood for the dam. Various design solutions have been proposed to secure and strengthen the radial gates, however an important concern is the potential for flow-induced vibration. Under extreme flood conditions, flows near the gate arms will be high-velocity, free-surface, with a steep angle of attack on the arm beams. Traditional hand calculations for computing vibrations are of limited applicability in this situation, and there is little published data available for this combination of flow conditions and arm geometry. A detailed study using CFD modelling of the potential for vibration around radial gate arms was carried out for Wyangala Dam. This paper presents the results of the validation and reveals some interesting flow patterns and vortex shedding behaviour.
Assessment of flow-induced vibration in radial gates during extreme flood
Learn more -
$15.00
2010 Papers
2010 – Deformation and dam safety of earthfill dams
Learn moreGavan Hunter and Robin Fell
Earthfill embankments in Australia have been widely used in dam construction since the start of the 20th century replacing the older puddle type and concrete corewall embankment designs. Most Australian dam portfolios will have one or more of these embankment types. A key component to the dam safety assessment of these dams is understanding their deformation behaviour, in particular the assessment of the future performance of these structures as they now reach ages of 40 to 80 years or more.
Learn more
This paper presents the findings of a study on the deformation behaviour of earthfill embankments. It draws on a database of 54 case studies from mainly Australia, the United States and Europe. It is a component of a broader study on the deformation behaviour of embankment dams undertaken as a research project at University of New South Wales earlier this decade.
The data presented in this paper allows dam owners and their consultants to compare the deformation behaviour of their dam to the performance of other similar earthfill dams in evaluating dam safety. Typical patterns of deformation behaviour are presented and guidance is provided on identifying trends in deformation behaviour that are assessed as “abnormal” and that may be potentially indicative of marginal stability. -
$15.00
2010 Papers
2010 – Emergency Release Capacity for Dams – International to Local Perspectives
Learn moreC.Johnson, D.Stephens, M.Arnold and N.Vitharana
As part of Melbourne Water’s dam safety upgrade program, emergency release capacity is being investigated at a number of dams. Recent work undertaken by the Water Resources Alliance (WRA) for Melbourne Water has highlighted the lack of current Australian guidelines for appropriate emergency release capacity. With no relevant ANCOLD Guidelines, current practice still references the 1990 USBR guidelines which relate the length of time to empty a reservoir to the hazard and risk associated with dam failure. As hazard category assessment criteria has been improved since and dam design and safety standards are more stringent, the applicability of the USBR criteria in today’s environment is under consideration.
Learn more
With the prevailing climatic conditions requiring the augmentation of Melbourne’s water supplies, the Tarago Reservoir was recently brought back into service. However, the dam lacked adequate emergency and environmental release capacity, with this being critical to manage construction flood risk for a pending filter raising project. Through an analysis of recorded inflow data, it was evident the existing scour facility had insufficient capacity to handle the recorded inflows, and would not be able to maintain the reservoir at an appropriate level during the proposed works. The length of time to empty the reservoir for the existing scour facility and the preferred scour upgrade option were calculated and it was found that by providing a new 1200mm scour facility, USBR emptying times were met or exceeded. The enlarged outlet capacity was also required to meet the new environmental flow requirements for the dam.
The paper will review international guidelines, share the experience of several Australian water authorities in assigning emergency release capacity for their dams, and discuss the specific work undertaken to provide suitable emergency release capacity at Tarago Reservoir for Melbourne Water. -
$15.00
2010 Papers
2010 – Application of Available Climate Science to Assess the Impact of Climate Change on Spillway Adequacy
Learn moreKeirnan Fowler, Peter Hill, Phillip Jordan, Rory Nathan, Kristen Sih
Although there are considerable uncertainties in the science of climate change, there is a growing recognition of the importance of the issue. Incorporation of climate change impacts is now required in policy guidance from several government authorities and it is prudent risk management to consider the effects of climate change in planning for water resource infrastructure, including assessment and design of dam upgrades. This paper describes the potential impact of climate change on extreme flood estimates and provides a case study for Dartmouth Dam in south-eastern Australia. Three inputs to flood estimation were considered according to the projected impact of climate change; namely design rainfalls, modelled losses and initial reservoir level. The relative influence of each of these factors is explored. Rainfall and losses had a similar (and opposite) influence on results and for this dam the reservoir level prior to the flood event had the largest influence on results. This case study demonstrates that the insights of climate modellers and hydrologists need to be integrated in order to provide defensible estimates of the impact of climate change in flood hydrology studies. Credible projections of changes in design rainfall intensities are required for the full range of exceedance probabilities across Australia.
Application of Available Climate Science to Assess the Impact of Climate Change on Spillway Adequacy
Learn more -
$15.00
2010 Papers
2010 – A Unique and Holistic Approach to the Erodibility Assessment of Dam Foundations
Learn moreRichard Herweynen, Colleen Stratford
Assessing the potential for erosion of foundation rock downstream of a spillway is a problem faced on many dams, whether new or existing. The problem is made particularly difficult not only due to the uncertainty in determining the erosion potential of the rock, but also due to the variable hydrologic characteristics of flood events.
The selected spillway option for Wyaralong Dam comprises a centrally located primary spillway with a secondary spillway located on the left abutment. A stilling basin energy dissipater is provided at the toe of the primary spillway. Downstream of the secondary spillway, an apron channel will direct flows back to the stilling basin. However, for flood events larger than the 1 in 2000 AEP event, the capacity of the secondary spillway apron is exceeded and flows spill out across the left abutment of the dam towards the river channel. Erosion of this left abutment was viewed to be a potential dam safety issue, and as such, careful consideration was required during the design stage to determine the acceptability of this spillway arrangement.
In order to provide structure to a problem which often relies solely on engineering judgment, a decision process was developed, taking into consideration some of the more definable aspects of the problem. These aspects included the geological characteristics, the initial hydraulic characteristics, the flood duration, the nature of erosion should it occur and the stability of the dam. This paper describes the decision process and methodology used at Wyaralong Dam to
determine the acceptability of erosion. This paper will present the process in a way that it can be used by others in future dam projects, both new and upgrades.A Unique and Holistic Approach to the Erodibility Assessment of Dam Foundations
Learn more