2000 – Development of a Comprehensive Approach to Consequence Assessment
P.I. Hill, D. Cook, R.J. Nathan, P.A. Crowe, J.H. Green, N. Mayo
This paper describes the development of a comprehensive approach to estimating the consequences of failure of a dam. The approach considers separately the consequences in terms of potential loss of life, economic loss and damage to the environment and the development and application of the method involved professionals from a wide range of disciplines. The method has been applied to 28 dams in NSW.
$15.00
Related products
-
$15.00
Papers 2000
2000 – Protecting Environment Flows While Catering for Urban Water Supply Demand – The Cowarra Off-Creek Dam Experience
Learn moreMurray Thompson and Geoff Chenhall
The Hastings District Water Supply Augmentation Scheme [HDWS] includes a 10GL off-creek storage dam, which is currently under construction and due for completion in October 2001. The Cowarra off-creek storage dam is required to meet predicted long-term urban growth demands for water supply and to ensure protection of environmental flows in the Hastings River.
Since 1985 the Hastings Council has progressively developed a strategy for the augmentation of the water supply scheme. A very successful ongoing consultation process with both the local community and key government agencies during the planning and implementation phases of this project has highlighted a number of key issues including:
“That the impact upon aquatic flora and fauna in the Hastings River should be minimised and appropriate safeguards developed by maintaining minimum river flows to ensure that the river habitat is not adversely affected”
The subsequent HDWS Environmental Impact Statement, 1995 was one of the first in NSW to recognise the importance of environmental river flows in the assessment of the aquatic ecological effects of water supply schemes. This paper to be presented to the ANCOLD Conference on Dams will detail the investigation, planning, implementation and current construction activities associated with the Cowarra Off-Creek Storage Dam.
Learn more -
$15.00
Papers 2000
2000 – Hume Dam Rehabilitation – An Owner’s Perspective
Learn moreDavid Dole and Brian Haisman
The $75 million remedial works at Hume Dam on the Murray River near Albury have been of national significance. The rehabilitation program associated with the structure itself and with its appurtenant works is now in the final steps of construction. The authors summarise this program with an emphasis not on technical details, but on decision processes. Equity in this dam is, in effect, held in equal parts by three State governments and by the Commonwealth government. At the same time, in response to the national water reform agenda, the governments have agreed upon new cost sharing arrangements that more nearly reflect the value of services to each government. The particular problems of decision-making within this evolving inter-State environment are discussed.
Lessons from experiments with application of risk analysis are discussed. Finally, the matter of adequacy of the structure for extreme floods is still under consideration. Hume Dam will presently pass the Design Flood developed in accord with Book VI (1999) of Australian Rainfall and Runoff, and the Dam Crest Flood has been estimated to have an annual exceedance probability of 1:110,000. _ Retrofitting a spillway to pass the estimated Probable Maximum Flood will double the cost of remedial works and is estimated at 10 times the cost of similar capacity built into original construction. The authors discuss the public policy elements of this pending decision.
Learn more -
$15.00
Papers 2000
2000 – Environmental Challenges in Constructing the Warragamba Dam Auxiliary Spillway
Learn morePieter van Breda, Peter Walton, Kate Lenertz and Tim Sheridan
The Warragamba Dam Auxiliary Spillway Project, designed to manage floodwaters up to a Probable Maximum Flood event, was approved by the NSW Minister for Urban Affairs and Planning on February 12, 1998. An Environmental Impact Statement prepared for this project predicted that noise, dust (suspended and deposited), blasting, vibration, water quality and revegetation would be the significant environmental issues requiring management throughout the construction phase.
The closest residents are approximately 200m from the construction activity. The works must not interfere with the operation of the Dam, which stores 80% of Sydney’s drinking water and the integrity of the existing infrastructure must be maintained at all times. The approved proposal was to emplace the 2.2Mm3 of spoil excavated to create the spillway in an area 25 ha by 20m high on top of a ridge on the left bank adjoining the Blue Mountains National Park. This created visual impact and rehabilitation challenges.
Although the contract for this project was primarily performance based, strict environmental clauses were incorporated to manage these priority issues. Noise and dust modelling were required from each pre-qualified Tenderer, to demonstrate capability of compliance with NSW Environment Protection Authority requirements. This formed part of the tender assessment. Criteria were also developed for revegetation, specifying numbers of endemic trees, shrubs and grasses per 400m2 of spoil emplacement in order to create a floral community similar to the existing adjacent National Park.
The implementation of these requirements and the development of a site Environmental Management Plan by the Sydney Catchment Authority, Australian Water Technologies and Abigroup Contractors, whilst maintaining productivity, has proven to be a working example of the benefits of Partnering.
Learn more -
$15.00
Papers 2000
2000 – Risk and Standards Based Approach to Rip Rap Design Alternative for Grahamstown Dam Stage 2 Augmentation
Learn moreM. B. Barker and D. Holroyde
A detailed study was completed for the Stage 2 works of the Grahamstown Dam augmentation to investigate various alternatives for the slope protection of the Saddle Dam and Subsidiary Dam embankments, including a standards based and a risk management approach. The standards based approach required an evaluation of the slope protection level and least cost option based on the hazard rating of the dam. Due to the sand construction of the embankments, it was possible to apply a wave erosion model SBEACH to develop an economic risk model for optimising the slope protection alternatives. The erosion model included the effects of the wind direction, reservoir level and wind speed variation during flood events, embankment profile and material parameters. The risk management approach clearly showed that significant cost savings could be achieved by using the risk management approach. Furthermore, the cost curves indicated the sections of the embankments for which present capital works would not be economically justified and for which ongoing maintenance works would be economically advantageous.
Learn more -
$15.00
Papers 2000
2000 – Capping of Very Low Strength Tailings Using Woven Geotextile and Geosynthetic Clay Liner
Learn moreRoss Stewart
This paper describes the use of a high strength woven geotextile and preloading to stabilise the surface of a very low strength tailings pond, and the incorporation of a geosynthetic clay liner (GCL) within the final capping design to complete closure. The pond, which contains tin and copper tailings, formed the lower tailings containment area of a three-tiered tailings storage, located directly above the Wild River in North Queensland. Stabilising the lower pond (area 2,500 m2), which contained tailings of “zero strength” in the central area involved the placement of a woven geotextile over the surface, which was anchored around the perimeter. The placement of finger berms (preloading fill) on the geotextile was successful without exceeding the bearing capacity of the tailings overall. Settlements of the berms were closely monitored to allow the system to support construction plant. After the finger berms were joined, they were widened until the area was covered. A sand layer was then placed over the area followed by a GCL to form an impermeable barrier prior to the placement of clay and topsoil.
Learn more