1998 – Matahima Dam Strengthening Project Management Design, Consents and Construction
Steve Everitt, Ron Fleming, Lelio Mejia
The Electricity Corporation of New Zealand Ltd (ECNZ) is strengthening its Matahina Dam which is an 80 m high, 400 m long rockfill dam impounding a 60 million cubic metre reservoir. The strengthening is to ensure the dam will withstand potential fault displacement within the dam foundation.
ECNZ’s management of the project is described from the design and consents phase through to construction. Key issues are discussed which have contributed to the success of the project such as management structure, the International Review Board, the design process and risk management.
$15.00
Now showing 1-12 of 31 2948:
Related products
-
$15.00
1998 Papers
1998 – Risk Assessment for Hume Dam – Lessons from Estimating the Chance of Failure
Learn moreLeonard A McDonald and Chi Fai Wan
A risk assessment has been undertaken as part of a comprehensive review of the safety of Hume Dam. Use of risk assessment techniques, to assist in evaluating the safety of existing dams, is a relatively recent trend. Hume Dam was a particularly challenging subject for the application of risk assessment techniques at their present stage of development. The challenge lay in the number and diversity of dam elements to be analysed, in the number and complexity of the potential failure modes and in the fact that there were significant safety issues under normal operating conditions.
This paper outlines some of the key lessons learned from that phase of the risk assessment that was concerned with estimating the chance of dam failure. Some of the issues discussed have not previously been addressed in the literature and some demonstrate a clear need for improved analysis procedures.
Learn more -
$15.00$0.001998 Papers
1998 – Characterisation of AAR-Affected Concrete From Dam Structures for Rehabilitation Purposes
Learn moreA Shayan
Alkali-aggregate reaction (AAR) is a potentially deleterious process in concrete containing reactive aggregates, and can lead to varying degrees of cracking in structures, and differential movement and misalignment of concrete elements and mechanical installations. The rehabilitation of affected structures would require information on the extent of current damage and possibility of on-going damage that could be caused by AAR.
Information on the characterisation of concrete components of an AAR-affected dam and estimation of their future potential for further expansion and cracking are provided and repair options discussed in this paper.
Learn more -
$15.00
1998 Papers
1998 – Initial Raising of Borumba Dam
Learn moreRA Geddes
Over the last 30 years, the demand for water storages in Queensland’s Mary’s River has grown significantly. As a result of this growth in demand it was decided to raise Borumba Dam, the major storage on the system, in two stages The first stage was to be approximately 2 metres in I997 and the 25 metre raising be required in about 2010.Borumba Dam was completed in 1964. It is a 43 metre high concrete faced dam with a 32 metre long on the left abutment. The first proposal for initial raising was to install a two metre high air-inflated rubber dam on top of the existing crest. However, it was determined that this method of raising presented a number of prob and a new solution was sought.
Learn more -
$15.00
1998 Papers
1998 – Results from The Earthquake Preparation, Alarm and Response System for Sydney Water Corporation, 1992 to 1998
Learn moreGary Gibson, Wayne Peck, Ian Landon-Jones and Kumara Arachchi
One of the first seismograph networks designed specifically to record local earthquakes was installed about Sydney in 1958. This network was converted to telemetry in 1983. In 1992, Sydney Water Corporation upgraded the network, integrating the functions of earthquake location and magnitude, measurement of the response of structures to earthquake motion, and provision of information for emergency response. The response function has been developed over the past six years, and is now an “Earthquake Preparation, Alarm and Response” system that provides customised information very soon after any significant event.
Learn more -
$15.00
1998 Papers
1998 – Liability for Dam Performance by Owners, Design and Constructors
Learn moreD. C. Green
The disaggregation of public water supply bodies in recent years has seen the functions of ownership, design and operation transferred to separate bodies. Consequently , issues of risk management associated with legal liability which previously could be ignored because all risks were absorbed in -house must now be faced and addressed in a more formal way.
This paper looks firstly at the general principles of legal liability for dam performance associated with construction and design, ownership of an existing dam and monitoring of its performance. Liability under several different areas of the law is discussed. Special issues associated with “design and construct” contracts are then highlighted, and warnings are given for project sponsors who control the letting of contracts and the briefing of consultants.
Learn more